Monday, December 29, 2014

December 29, 2014 Update Of Phase 2 Fence Project

 Trenching Done And Poles Ready To Be Installed Towards West Ramp

 Poles Installed Along Wadsworth Road Towards Baxter

 Fence Fabric Installed On Portion Looking Towards Greenbay Road

Black Vinyl Fence Installed Around Baxter Entrance Road

 Vinyl Coated Gate Installed At Baxter

Fabric For Fence Installed From Lewis Avenue

View Where Fabric Installation Has Stopped, Looking Towards Greenbay Road

Wednesday, December 24, 2014

December 23, 2014 Fence Project Phase 2 Update

Fence Area Looking Towards Wadsworth Road Cleared And Ready For Trenching

 Same Area Looking Away From Wadsworth Road Towards Airport

New Fence On Wadsworth Road Towards Baxter



Looking Towards Greenbay Road

Monday, December 22, 2014

Update Of Phase 2 Fence Project December 20, 2014

Lighted X Out For Closure Of Runway 14/32 As Work Continues On The Fence Project

 Trenched Finished Along Wadsworth Road and Ready For The Post


Thursday, December 18, 2014

Phase 2 Fence Project December 18, 2014

 Actual Fence Fabric Installed. About 250 feet From Lewis Avenue

Top Posts And Barbed Wire Angle Bracket Installed


Black Vinyl Post By Baxter's Gate Starting To Be Installed

View On Wadsworth Road Looking Towards Greenbay Road

View On Wadsworth Road Looking Towards Lewis Avenue

Monday, December 15, 2014

December 15, 2014 Phase 2 Fence Project Update

Kind Of Foggy Today, But Some Top Rails Were Installed



Cement For Post Also Getting Done Today

Friday, December 5, 2014

Phase 2 Fence Project December 5, 2014

Fence Post Are In Place  Looking Towards Lewis.

 More Posts In Looking Towards Greenbay Road.

 A Bit Further Towards Greenbay Road The Auger Continues.

Grubbing Towards Greenbay Road Continues Also.


Wednesday, December 3, 2014

Phase 2 Fence Update December 3, 2014

 ComEd doing some repairs to a line that was struck last week.


 Auguring for the posts.


 More Trenching continuing for the underground portion of the fence.

 Grubbing of the shrubs and trees started.




Thursday, November 20, 2014

OMG! The Phase 2 Fence Project Started!!

Miracles Do Happen! Today There Was Work Done On The Fence, Phase 2!



For A Project That Was Supposed To Start In May 2014, It's A Start! More Later