Monday, December 5, 2011

December 5, 2011 - Dumpster Gate Installed??!!

Can You Believe That We Now Have A Gate!?
SHOCKER!!
 It's Only Taken A Year, But It's Here!
   Better Late Than Never. Woot Woot!

Wednesday, July 6, 2011

We Are IN!! (Actually Have Been For A Few Weeks)

Ribbon Cutting Ceremony
Oh Yeah, It's My Building!
Some Vehicles Parked Inside

Duncan Giving A Nice Opening Day Speech!
Could Be A Mob Action!

Wednesday, June 8, 2011

SRE Update: June 8, 2011..Looks Like It Could Be Done June 10!!!!!

All Seeding Done

Air Conditioner Installed
Awning And Gutters Finished As Well
Fridge And Microwave Are In
Dry Erase Board Is Installed As Well
Shower Curtain, Errr Washbay Curtain Installed
Hot Water Heater, And Air Compressor Are In Working Order

Saturday, May 21, 2011

SRE Update: May 19 & 20 Closer Yet To Being Done

The Parking Lot is Now Done!


Landscaping Started Also


Soon Grass Will Be Here
A Look At The Storm Water Outlet
A View From Across The Street








Wednesday, May 11, 2011

SRE Update: May 9 2011 Concrete Finished

West Entrance Concrete Started
South Side Getting Ready Also
May 6th Pavement Saw Cut

Sidewalk Finished

View Of The West Entrance Finished
Southside Getting Finished Now

May 11 Views Of The Saw Cuts



Sunday, May 8, 2011

SRE Update: May 6, 2011 Another Big Step

Curbs Are In For Parking Lot

Forms For Concrete Portions In Place

Just About Ready For The Pour
And It Begins, A Year Late, But It's Is Starting
The Concrete Ramps Are Going In

Looks Good, And Can't Wait To Drive On It
Around The Corner, Looking Towards Plane Rest Drive