Trenching Done And Poles Ready To Be Installed Towards West Ramp
Poles Installed Along Wadsworth Road Towards Baxter
Fence Fabric Installed On Portion Looking Towards Greenbay Road
Black Vinyl Fence Installed Around Baxter Entrance Road
Vinyl Coated Gate Installed At Baxter
Fabric For Fence Installed From Lewis Avenue
View Where Fabric Installation Has Stopped, Looking Towards Greenbay Road
A site where you can keep up to date on everything going on at the Waukegan National Airport.
Monday, December 29, 2014
Wednesday, December 24, 2014
December 23, 2014 Fence Project Phase 2 Update
Fence Area Looking Towards Wadsworth Road Cleared And Ready For Trenching
Same Area Looking Away From Wadsworth Road Towards Airport
New Fence On Wadsworth Road Towards Baxter
Looking Towards Greenbay Road
Same Area Looking Away From Wadsworth Road Towards Airport
New Fence On Wadsworth Road Towards Baxter
Looking Towards Greenbay Road
Monday, December 22, 2014
Update Of Phase 2 Fence Project December 20, 2014
Lighted X Out For Closure Of Runway 14/32 As Work Continues On The Fence Project
Trenched Finished Along Wadsworth Road and Ready For The Post
Trenched Finished Along Wadsworth Road and Ready For The Post
Thursday, December 18, 2014
Phase 2 Fence Project December 18, 2014
Actual Fence Fabric Installed. About 250 feet From Lewis Avenue
Top Posts And Barbed Wire Angle Bracket Installed
Black Vinyl Post By Baxter's Gate Starting To Be Installed
View On Wadsworth Road Looking Towards Greenbay Road
View On Wadsworth Road Looking Towards Lewis Avenue
Top Posts And Barbed Wire Angle Bracket Installed
Black Vinyl Post By Baxter's Gate Starting To Be Installed
View On Wadsworth Road Looking Towards Greenbay Road
View On Wadsworth Road Looking Towards Lewis Avenue
Monday, December 15, 2014
Friday, December 5, 2014
Phase 2 Fence Project December 5, 2014
Fence Post Are In Place Looking Towards Lewis.
More Posts In Looking Towards Greenbay Road.
A Bit Further Towards Greenbay Road The Auger Continues.
Grubbing Towards Greenbay Road Continues Also.
More Posts In Looking Towards Greenbay Road.
A Bit Further Towards Greenbay Road The Auger Continues.
Grubbing Towards Greenbay Road Continues Also.
Wednesday, December 3, 2014
Phase 2 Fence Update December 3, 2014
ComEd doing some repairs to a line that was struck last week.
Auguring for the posts.
More Trenching continuing for the underground portion of the fence.
Grubbing of the shrubs and trees started.
Auguring for the posts.
More Trenching continuing for the underground portion of the fence.
Grubbing of the shrubs and trees started.