Thursday, August 26, 2010

SRE Building - In the Beginning!




March 17......The area where shop will be located.
June 1......Still no activity, but a lone stake is in the ground!
July 2....Activity in getting the area ready.

Some of the footing's done, but not all.

July 23....Footing's all finished being dug, filled with rain water.

July 29...Pouring the first footings for the Sand Storage room.





Thursday, August 19, 2010

Check out our new Snow Plow Truck

I had the opportunity to visit the shop that is putting the add-on parts on snow plow in Monroe, Wisconsin.  Here are some pictures.
Inside of Truck... Sweet!