Perimeter Fence Project Phase 3 Update
SRE/Plane Rest Drive Gate installed. Not Electrically Operational Yet
Airport Ops Office Gate Goes Here, But Fence Is Installed
South & North Parking Lot Fence Installed, As Well As The South Ramp Gates
Landmark's Ramp Gates Installed
Grainger Gate Installed
Fence From Grainger To Fuel Farm Installed
Airport Ops Office Gate Goes Here, But Fence Is Installed
South & North Parking Lot Fence Installed, As Well As The South Ramp Gates
Landmark's Ramp Gates Installed
Grainger Gate Installed
Fence From Grainger To Fuel Farm Installed
Tuesday, July 7, 2015
July 7, 2015 Phase 3 Fence Update
The Moved Gate 4 Installation Begins
Fence Post Installed Between The Two Hangars On McAree Road
South Ramp Fence Post Installed By Self Serve Fuel Station
Fence Post Installed Between The Two Hangars On McAree Road
South Ramp Fence Post Installed By Self Serve Fuel Station
Thursday, June 25, 2015
Perimeter Fence Project Phase 3 Update
Looking From Hickory Street Towards Oak Street
Looking Back At Stump Grinder Near Hickory Street
Loading Trailer Parked On Oak Street With Brush From Old Fence Line
Wood Chipper & Trailer Parked On Oak Street
Looking Away From Oak Street Towards Lewis Avenue
Looking Back Towards Oak Street Houses
These Next Three Pictures Are The Final Leg Connecting Fence To Lewis Avenue
Looking Back At Stump Grinder Near Hickory Street
Loading Trailer Parked On Oak Street With Brush From Old Fence Line
Wood Chipper & Trailer Parked On Oak Street
Looking Away From Oak Street Towards Lewis Avenue
Looking Back Towards Oak Street Houses
These Next Three Pictures Are The Final Leg Connecting Fence To Lewis Avenue
Wednesday, June 17, 2015
Update of the Phase 3 Perimeter Fence Project
These are trenches for the Plane Rest Drive Gate. Power will come from our vault.
The gate is being moved in farther for easy public access to the airport office's.
More pipe trenched in from the vault to Plane Rest Drive.
Pipe not yet trenched in from the vault to the new electric pedestrian gate.
Old fence at the Operations Office removed, with some temporary poles installed
These next two pictures are from the start of install on McAree Road looking west.
The gate is being moved in farther for easy public access to the airport office's.
More pipe trenched in from the vault to Plane Rest Drive.
Pipe not yet trenched in from the vault to the new electric pedestrian gate.
Old fence at the Operations Office removed, with some temporary poles installed
These next two pictures are from the start of install on McAree Road looking west.
Wednesday, June 10, 2015
Perimeter Fence Project Phase 3
Started the last week of May, the Perimeter Fence Project Phase 3 began.
These are from Yesterday, June 9th looking towards McAree Road.
These are from June 10, 2015. Fence going up from start of entrance road.
New 20 foot manual gate here on entrance road.
These are from Yesterday, June 9th looking towards McAree Road.
These are from June 10, 2015. Fence going up from start of entrance road.
New 20 foot manual gate here on entrance road.
Wednesday, January 28, 2015
Perimeter Fence Project Phase 2 Update January 28, 2015
End Of Aviation Drive
All Barbed Wire Installed
Looking Towards Wadsworth Road From Aviation Drive
Obstruction Lighting In Place Along Wadsworth Road, Approach End Of Runway 14
Construction/Maintenance Gate Installed At Wadsworth Road
Black Vinyl Meets Standard Fence At Baxter
Black Vinyl Gate Installed At Baxter As Well
End Of Black Vinyl Fence Looking Towards Lewis Avenue On Wadsworth By Baxter
Looking Towards Approach End Of Runway 23 On Wadsworth
On Wadsworth looking Towards Lewis Avenue
Corner Post Where Phase 1 and Phase 2 Fence Meet At Wadsworth And Lewis Avenue
All Barbed Wire Installed
Looking Towards Wadsworth Road From Aviation Drive
Obstruction Lighting In Place Along Wadsworth Road, Approach End Of Runway 14
Construction/Maintenance Gate Installed At Wadsworth Road
Black Vinyl Meets Standard Fence At Baxter
Black Vinyl Gate Installed At Baxter As Well
End Of Black Vinyl Fence Looking Towards Lewis Avenue On Wadsworth By Baxter
Looking Towards Approach End Of Runway 23 On Wadsworth
On Wadsworth looking Towards Lewis Avenue
Corner Post Where Phase 1 and Phase 2 Fence Meet At Wadsworth And Lewis Avenue