A site where you can keep up to date on everything going on at the Waukegan National Airport.
Tuesday, August 31, 2010
Sunday, August 29, 2010
Runway 14 - 32 Overlay
August 27...32 Portion Painting Finished
August 18...Runway 14 final lift
August 27...14 End With Dirt Work Started
August 27...Dirt Work Mid Field 14/32August 18...Final lift of Runway 32 pavement
August 18...Runway 14 final lift
SRE Building - Storm Drains Installed/ Inside Building Drains Installed
August 27...Area for "The" Sink
August 27...Oil Separator's Installed
August 27...Middle of SRE With Center Drain
August 27...Oil Separator's Installed
August 27 ... Overview
August 27 ... Car Parking Lot
August 27...East Entrance With Door Drain Installed
August 27..."Vault" and Drain For Wash Bay
August 27...South Side Concrete Drive Portion
Friday, August 27, 2010
SRE Building - Sand Room and Some Rough Plumbing!
Aug 19 ...Sand Room just before the walls are poured.
Aug 19...Storm water piping going in.
Aug 19 ...Plumbing for restrooms roughed in.
Aug 19...The cement pump for Sand Room walls.
SRE Building - More Walls Being Formed!
Aug 13... Inside of shop looking towards Sand Room
Aug 13... View of greeting area.
Aug 13... The airport Maintenance Supervisor's office.
Aug 13... Looking at Sand room.
Aug 13...Over view of SRE on August 13, 2010, pouring the final office walls.
Thursday, August 26, 2010
SRE Building - Walls Being Formed!
Aug 6....All footings in, now forming walls.
Aug 6 .... Wall formed looking at Sand Storage area.
Aug 6...Walls formed looking South and East.
Subscribe to:
Posts (Atom)