 These are trenches for the Plane Rest Drive Gate. Power will come from our vault.

The gate is being moved in farther for easy public access to the airport office's.



 More pipe trenched in from the vault to Plane Rest Drive.

Pipe not yet trenched in from the vault to the new electric pedestrian gate.

 Old fence at the Operations Office removed, with some temporary poles installed

These next two pictures are from the start of install on McAree Road looking west.